3. SUMMARY OF CONCLUSIONS AND RECOMMENDATIONS
This section summarises the major conclusions and recommendations
presented in greater detail in the report. Specific recommendations
are made for the provision of hardware and staff for the
period 1976-78.
Budgetary figures are provided for the period beyond 1978.
3.1 Conclusions
3.1.1 User Needs for Interactive Computing
There is a substantial and immediate need for additional
interactive computing for engineers engaged on SRC funded research.
The existing user population (including research students) is about
900 with a requirement for processing power for interactive use of
about 7 Atlas units compared with about 2 units available from SRC
funded interactive computers. It is estimated that the user population
will increase to about 1300 by 1978 and it is judged that a deliberate
attempt should be made to increase the computing power available for
interactive purposes to about 28 Atlas units by 1980
(See Sections 5.4 and 6.5.1).
3.1.2 User Needs for Access to Large SRC Computers
Besides their needs for interactive computing some engineers will
continue to need access to the largest available batch processing
machines and some engineers will require access to large processing
power through the interactive system. The latter will require a link
to the 360/195 at Chilton. It is estimated that the demand on the
360/195 from this source will rise to 0.4 of a 360/195 by 1979
(See Section 5.6).
3.1.3 Computer Costs
For small computers the costs of central processor power, memory
and to a lesser extent, peripherals are decreasing rapidly and are
expected to decrease further over the next five years.
The processing power of "small" machines is increasing and mini
computers (eg GEC 4080) have reached about 1 Atlas. Costs of
software are increasing as a proportion of the total investment in
computing (See Appendix 2).
3.1.4 Communications
Future communication costs in the UK are uncertain.
The recommendations given below are very dependent upon the provision
of an integrated interconnected system. The proposals for the period
1976-78 can be implemented using star networks including the
substantial system already set up by the SRC. The existence of a
general purpose switching network would improve these facilities and
is essential for the longer term
proposals (See Appendix 1 and Section 6.5).
3.2 Hardware Recommendations for Period 1976-78
It is recommended that:
- A central system of at least 3 x Atlas should be installed
at Chilton to satisfy the needs of 600 users (Cost £lM)
(Section 6.2.1).
- The UMIST PDP KA1O interactive system should be enhanced to
provide a general service for 150 users. The facility should cease
to be associated with a specific research project and should be a
general SRC Engineering Board facility. The Director of the
Rutherford Laboratory should be responsible for it. (Cost £160K)
(Section 6.2.1).
- The Edinburgh PDP1O system should continue to be treated as a
general SRC Engineering Board facility but should be expanded to
provide a service for 250 users. The Director of the Rutherford
Laboratory should be responsible for it. (Cost £220K).
(Section 6.2.1).
- Funds should be provided for the enhancement of 5 existing mini
computers in university departments to bring them to multi-user
capability. The aim should be for them to satisfy 50 users each.
(Cost £160K). {Section 6.2.1).
- Two multi-user minis should be purchased for development purposes.
The Rutherford Laboratory should be responsible for this development
in conjunction with university groups. The aim of this work should be
to assess accurately the future capability of such systems rather
than to provide facilities in the short term. (Cost £160K)
(Section 6.2.1).
- A sum of £540K should be provided for the purchase of
terminals (Section 6.2.2).
- A sum of £50K should be provided for capital equipment for
network research (Section 6.2.3).
- A sum of £620K should be provided for communications
equipment (Section 6.2.3).
These recommendations will involve capital costs of £3.0M
and will provide
facilities for 1250 users by 1978 although the processing power falls
considerably short of the requirements at that stage (see
Section 6.5.1).
3.3 Other Recommendations for Period 1976-78
It is recommended that:
- A strong attempt should be made to reduce unnecessary duplication
in development of software packages and to provide adequately
documented software for general use. The general policy should be to
provide given packages only at a single site and all users can then
gain access through the interconnection of all facilities.
Qualified staff should be provided at Chilton to
assess user needs and to mount selected packages (including industrial
and commercial packages where appropriate) at the relevant machine.
No staff for writing new packages should be provided until a case
is made and accepted. (Section 6.3.1).
- Preparation of some of the existing applications software for
general service must be one of the first tasks undertaken.
In particular an interactive FORTRAN library should be established
and co-ordinating and documenting for all levels of graphics software
should be started. (Section 6.3.1).
- A Bulletin or Newsletter related to the work of the proposed
interactive service should be established and published regularly.
(Section 6.3.2).
- Resources should be made available to finance applications workshops,
conferences and development of the Meeting House function.
(Section 6.3.3).
- Encouragement should be given to British manufacturers to provide
suitable multi-user minis by the early notification of specifications
and future requirements. This also applies to terminal and communication
equipment. (Section 6.2.1).
The recommended direct staff at Chilton and at universities is
given in Table 6.4 in Section 6.4.3 and the recurrent costs
arising from this and other sources are summarised in Table 6.6 in
Section 6.4.5.
3.4 Recommendations for Period beyond 1978
- It is recommended that a further review be made in 1977/78 to
establish definite plans for the considerable enhancement that will be
required to the proposed system, particularly in processing power.
(Section 6.5).
- For budgetary purposes capital and recurrent expenditure is
estimated on the assumption that multi-user minis become cheaper
than current prices by a factor of two by 1980 in real terms, and
that improvements to hardware and software continue. Table 6.8 in
Section 6.5 gives these budgetary estimates and Table 6.9 combines
the total estimates for the whole period 1976-81. The total capital
is £4.0M and recurrent expenditure reaches £1.3M per year in
1981.
3.5 Management
Central to the whole of the plan presented is the concept that the
SRC should provide an integrated and co-ordinated service for
interactive computing for engineers. To achieve these ends it is
recommended that:
- An Engineering Computing Facilities Committee should be
appointed by the Engineering Board with duties as described in
Section 8.1. A Users' Sub-Committee should also be appointed.
(Section 8.1).
- The Director of the Rutherford Laboratory should be responsible
for implementing the recommendations of this report and should have
overall responsibility within the SRC for all the facilities
concerned. (Section 8.1).
It will be essential if the needs of users are to be adequately met
for the facilities to be run by staff who arc, familiar with
engineering needs, with the hardware and software available to
meet these needs, and with the progress of relevant engineering
research. (Section 6.4.1).
- Suitable arrangements should be negotiated with universities and
polytechnics at which computers or terminals are to be
located. (Section 8.2).