ACLTechnologyAtlas Building :: Atlas Building
ACLTechnologyAtlas Building :: Atlas Building
ACL ACD C&A INF CCD CISD Archives
Further reading

Overview
Finding a site
1962
Early 1963
Late 1963
February 1964
March 1964
July 1964
Phase 2: 1966
Phase 2: 1967
Phase 2: 1967
Fish tank
1971 onwards

Autumn 1966

The amount of office space available was always a problem and Phase 2 was started two years after the completion of Phase 1. The initial plans always had the concept of filling in the other sides of the rectangle started by the first Office Block. By 1966, the existing building had a reasonably mature look about itself. the plan was to add an Office Block along the road connected to the existing Office Block.

Atlas Building: September 1966

Atlas Building: September 1966
Full image ⇗
© UKRI Science and Technology Facilities Council

The digger arrives

The digger arrives
Full image ⇗
© UKRI Science and Technology Facilities Council

By November, the foundations were beginning to take shape. This view looks out towards the main road.

Foundations

Foundations
Full image ⇗
© UKRI Science and Technology Facilities Council

By December, the foundations were pretty well complete.

Foundations: December 1966

Foundations: December 1966
Full image ⇗
© UKRI Science and Technology Facilities Council